Want to know more?
Find out more about how Energy Systems Catapult can help you and your teams
Get in touch
Want to know more?
Find out more about how Energy Systems Catapult can help you
Speeding up the delivery of strategic electricity transmission lines is challenging but vital and achievable, finds an independent report by the Electricity Networks Commissioner Nick Winser.
The UK has been successful in stimulating investment in generation from renewables in recent decades, but this has not been matched with investment in electricity transmission networks. Meaning the ‘queue’ to connect to the grid is extremely congested, with more than 230GW of generation waiting, compared to c.80GW of generation currently connected.
The former National Grid UK CEO and current Energy Systems Catapult chair, Nick Winser, found that the current length of time taken to build new electricity transmission from identification of need to commissioning was 12 to 14 years – large wind farms are built in half this time.
Renewable energy developers and other connection customers are currently receiving connection offers for the 2030s, slowing the clean energy transition. While annual constraint costs – paid to generators to switch off when supply outstrips demand – could rise from around £0.5-1 billion per year in 2022 to a peak of £2-4 billion per year around 2030 if all current investment is delivered on time.
The Electricity Networks Commissioner was appointed in July 2022 and tasked with providing advice to Government on how to reduce the time it takes to deliver transmission infrastructure in Britain. The Commissioner has now delivered his report as a letter to Rt Hon Grant Shapps, Secretary of State for the Department for Energy Security and Net Zero.
With very few new transmission lines built in the last 30 years and a dramatic increase needed through to 2050 to achieve Net Zero targets, Mr Winser said even these long timescales may be challenging to meet if we fail to streamline the process.
The Electricity Networks Commissioner report sets out 18 Recommendations and supported by a detailed companion report by Energy Systems Catapult finds that the delivery time for strategic transmission lines can be reduced to around seven years.
Electricity Networks Commissioner, Mr Nick Winser, said: “Delivering 50GW of new wind power and 24GW of new nuclear will be a major step towards decarbonising our economy and providing customers with clean, secure, affordable electricity, but that magnificent achievement will be wasted if we cannot get the power to homes and businesses.
“The implications of being able to build wind generation faster than the associated connections to customers will be serious: very high congestion costs for customers, and clean, cheap domestic energy generation standing idle, potentially for years.
“So, the challenge to me, set by the Secretary of State at the time, to reduce the timescale for building strategic transmission by three years, and ultimately by a half is the right one. I believe that we must hit the more ambitious end of this and reduce the overall timescale to seven years.
“I am confident that this is achievable as long we streamline the process as proposed in the report; and take a transparent, respectful and efficient approach when engaging with people and communities about the impact.”
Mr Winser said the current process is complex and involves many different parties, including:
Mr Winser said: “Every part of this process must – and can – be dramatically improved including introducing a spatial energy plan and design principles outlining where and why we need new lines, and how both the environmental and economic impacts have been considered.
“Many significant improvements have been introduced in recent years and my recommendations support and seek to build on this excellent work.”
Future System Operator: With the aim of being established by 2024 under the Energy Security Bill, this new body will bring together the planning for the electricity and gas systems, and potentially systems for new technologies like hydrogen and carbon capture and storage, into a single institution to enhance Britain’s ability to transition to a zero-carbon energy system and reduce the costs involved. The FSO will build on the existing capabilities and functions of the Electricity System Operator.
Transmission Operators: The three companies that own and operate the high voltage electricity transmission infrastructure in Britain – National Grid Electricity Transmission, Scottish Hydro Electric Transmission Ltd. and SP Energy Networks – and connect with the fourteen Distribution Network Operators across regions.
Until recently, identification of electricity transmission need has been a slow, iterative, and case-by-case process. The excellent work of the Holistic Network Design (published in July 2022) provides a strategic blueprint for the coordinated connection of 23GW of offshore wind to the network by 2030. However, this should go further and faster.
The Future System Operator (FSO) should be established quickly and be responsible for producing a Strategic Spatial Energy Plan (SSEP)
We need a SSEP for Great Britain. To reduce energy bills as much and as quickly as possible, we need bold decisions on energy policy right across the system. It is unrealistic to imagine that we can wait and see what energy sources and demands arise, then hope to build the necessary networks in time, so a SSEP will forecast the supply and demand characteristics and their likely whereabouts.
The FSO, supported by Ofgem, should urgently assess the scope for new short-term and long-term regional flexibility markets
Although this recommendation does not directly lead to shorter delivery times for electricity transmission, demand flexibility and smart investment and operation of energy storage facilities can reduce the need for new transmission investment. Urgent development of zonal flexibility markets and new, more encouraging, planning and operation rules will reduce transmission investment costs and provide valuable opportunities to deploy more renewables earlier.
The planning process is where individuals and communities can influence the plans, however currently each application appears before individuals, communities, the Planning Inspectorate, local authorities, and national governments with little political or engineering context being established previously or at a system level. A consultation on the revised energy National Policy Statements (NPS) proposes amendments to bring forward new transmission infrastructure by reflecting the importance of strategic network planning and clarifying presumptions, including for example, on when underground cabling may be used.
National Policy Statements should be updated urgently and regularly thereafter
Helpful changes to the National Policy Statements are currently being consulted on and should be updated routinely every five years. In addition, the Energy NPS should be updated to reflect the recommendations in this report.
A new document Electricity Transmission Design Principles should be created
The Electricity Transmission Design Principles (ETDP) will provide be a public document detailing the principles and methods used to design the system and decide the configuration of assets; onshore or offshore, overhead or underground. This will give a clear basis for communities and other stakeholders to understand proposals and a clear foundation for the Planning Inspectorate’s consideration. It could also be used to drive innovation and best practice sharing.
The regulatory process has evolved from considering individual transmission lines to groups of them, but it is not settled, streamlined, regular and operating at a system level. It still adds uncertainty and significant time to the process – this is time we cannot afford.
Ofgem should urgently conclude the Future Systems and Network Regulation consultation and establish a new regulatory arrangement with the Transmission Operators
There should be a strong and heavily incentivised responsibility on Transmission Operators to deliver to time and cost. And returns to shareholders should reflect this. Successful delivery should lead to superior returns, unsuccessful delivery to lower returns. These incentives should be reinforced by a strong emphasis on their licence obligation to provide an efficient, coordinated and economic system.
People and the communities in which they live and work will be impacted by new transmission infrastructure. These impacts may be seen as negative (e.g. loss of visual amenity) or positive (e.g. economic opportunities). But in either case, there is a need for constructive engagement and agreed public rules or guidance on community benefit, so affected individuals and communities have clear information to enable proper individual and collective assessment.
The FSO and TOs should work with the Government to design and implement a focused information campaign on the need for a grid refresh
The next three decades will see a significant upgrade to our electricity transmission system. The importance of this work to our country and to the environment needs to be communicated to the whole population so that when individual proposals for reinforcement are made, communities have some context in which to view them.
A clear and public set of guidelines for Community benefit should be established
Following the recent DESNZ consultation on community benefit, Government and Ofgem should agree and publish guidelines on benefit sharing for individuals and communities affected by new or upgraded transmission lines.
We suggest two components:
Electricity Networks Commissioner report by Nick Winser - Letter to Secretary of State for the Department for Energy Security & Net Zero
DownloadElectricity Networks Commissioner - Companion report by Energy Systems Catapult
Find out moreWe equip you with the evidence, insights and innovations needed to deliver the future Net Zero energy system
Find out moreFind out more about how Energy Systems Catapult can help you and your teams
Find out more about how Energy Systems Catapult can help you